| AGENCY/BUREAU | TAFS | Award Type | Total Obligations | Total Gross Outlays | Direct or Reimb-ursable | Ordering TAFS |
| (014-05) Department of State: Administration of Foreign Affairs | (19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act | Contracts and Orders (including modifications) | 23,319,565 | 7,069,475 | Direct | |
| (014-05) Department of State: Administration of Foreign Affairs | (19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act | Other | 508,634 | 250,914 | Direct | |
| (014-05) Department of State: Administration of Foreign Affairs | (19-4519 \ X ) Working Capital Fund | Other | 308,115 | 206,687 | Reimbursable | (19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act |
| (014-05) Department of State: Administration of Foreign Affairs | (19-0112 2009 \ 2010) Diplomatic and Consular Program, Recovery Act | Other | 919,860 | 323,223 | Reimbursable | [15-9-0700] Justice |
| (014-05) Department of State: Administration of Foreign Affairs | (19-1119 2009 \ 2010) Capital Investment Fund, Recovery Act | Contracts and Orders (including modifications) | 143,726,829 | 58,803,143 | Direct | |
| (014-05) Department of State: Administration of Foreign Affairs | (19-1119 2009 \ 2010) Capital Investment Fund, Recovery Act | Other | 66,254 | 59,290 | Direct | |
| (014-05) Department of State: Administration of Foreign Affairs | (19-4519 \ X ) Working Capital Fund | Other | 4,331,157 | 1,446,449 | Reimbursable | (19-1119 2009 \ 2010) Capital Investment Fund, Recovery Act |
| (014-05) Department of State: Administration of Foreign Affairs | (19-1079 2009 \ 2010) Construction, IBWC, Recovery Act | Contracts and Orders (including modifications) | 165,633,034 | 53,515,767 | Direct | |
| (014-15) Department of State: International Commissions | (19-1069 \ 2009) Salaries and Expenses, IBWC | Other | 689,846 | 689,846 | Direct | |
| (014-05) Department of State: Administration of Foreign Affairs | (19-4519 \ X ) Working Capital Fund | Other | 20,000 | 15,873 | Reimbursable | (19-0530 2009 \ 2010) Office of the Inspector General, Recovery Act |
| | | | | | |
| As of November 3, 2009, OMB has instructed the Department not to report on interagency transfers unless State is the receiving agency. Thus, while the Department has obligated $505,806,010.76, the report only totals $339,523,294. |
| | | | | | |
| MAJOR COMPLETED ACTIONS (Short bulleted list of the major actions taken to date.) | MAJOR PLANNED ACTIONS (Short bulleted list of the major planned actions) | | | | | |
| Consular Affairs: The pre-construction meeting for the new San Diego passport agency took place on July 27. | Data Center: Continued to receive and inventory ESOC (Enterprise Server Operations Center) West IT infrastructure hardware | | | | | |
| International Boundary and Water Commission (IBWC): Issued payment in the amount of $1,430,244.29 on 7/26/2010 for construction services of the North Floodway 1&2 and Arroyo Colorado 1&2 levee segments of the Lower Reach. | Data Center: Continue to review ESOC (Enterprise Server Operations Center) design documentation in phases as scheduled and received | | | | | |
| IBWC: Issue construction services solicitation for the Sunland Park levee segment of the Upper Reach. | | | | | |