| MAJOR COMPLETED ACTIONS (Short bulleted list of the major actions taken to date.) | MAJOR PLANNED ACTIONS (Short bulleted list of the major planned actions) | | | | |
| International Water and Boundary Control (IBWC): Disbursed $6,076,956 in payments | IBWC: Issue task order for the design of an additional 600 feet in the North Banker Floodway segment of the Lower Reach (est. 6/15) | | | | |
| IBWC: $218,068 against contract for the geotechnical investigations of Lateral A to Dunna Pump segments to Retamal Levee segments in the Lower Reach | IBWC: Issue task order for bid/construction services for the Banker Weir segment in the Lower Reach (est. 6/15) | | | | |
| IBWC: $5,858,888 against contract for the design of the Main and North Floodway and Arroyo Colorado segments in the Lower Reach | Consular Affairs: Scheduled site visit to St. Albans, VT for June 17 and 18 | | | | |
| IBWC: Corrected the $242,725 deobligation to correct function code on purchase request; obligation with the correct function code was processed on 6/11/09 | Consular Affairs: Awaiting confirmation from GSA to schedule site visit to El Paso, TX | | | | |
| IBWC: Completed Environmental Assessment and Cultural Resource Survey and issued a finding of No Signification Impact (FONSI) on June 11 for the Arroyo Colorado segment in the Lower Reach | Consular Affairs: GSA Texas currently in the process of posting the procurement advertisement for El Paso, TX | | | | |
| IBWC: Received final (100%) design for the North Floodway and Arroyo Colorado levee segments (June 12) and the final (100%) for the Main Floodway segment (June 5) of the Lower Reach | | | | | |
| Consular Affairs: Site visit to three potential locations in Buffalo, NY; GSA currently reviewing sites | | | | | |
| Hard Skills Training Center: With GSA project team, conducted initial screening of sites | | | | | |